Case Study: Six-Phase Relay Protection Tester Supports Commissioning at Zhuhai Combined Cycle Power Plant

July 7, 2026

Latest company case about Case Study: Six-Phase Relay Protection Tester Supports Commissioning at Zhuhai Combined Cycle Power Plant
Project Overview

Reliable relay protection systems are essential for the safe operation of modern power plants. During commissioning and maintenance, relay protection devices, synchronizing equipment, and fast transfer systems must be thoroughly verified before generating units are placed into service.

In February 2025, HKVTEST engineers provided urgent on-site technical support for a customer involved in commissioning work at a combined cycle power plant in Zhuhai, China. The project included relay protection testing, fast transfer device verification, generator synchronization testing, and operator training using the HZJB Six-Phase Relay Protection Tester.

latest company case about Case Study: Six-Phase Relay Protection Tester Supports Commissioning at Zhuhai Combined Cycle Power Plant


Project Background

A power engineering contractor urgently contacted HKVTEST after its relay protection tester failed during an ongoing commissioning project.

Because the replacement equipment was required immediately to avoid delaying the project schedule, HKVTEST arranged rapid delivery and dispatched an experienced technical engineer to provide both equipment support and on-site guidance.

The commissioning work was carried out at a combined cycle gas-fired power plant, where relay protection verification was being performed on auxiliary power systems and generator synchronization equipment.

latest company case about Case Study: Six-Phase Relay Protection Tester Supports Commissioning at Zhuhai Combined Cycle Power Plant


Project Challenges

The project presented several technical challenges:

  • The original relay tester failed during commissioning.
  • Tight project deadlines required immediate replacement.
  • Synchronizing devices had to meet strict voltage and frequency requirements.
  • Multiple relay functions required verification before unit startup.
  • Customer engineers needed training on the new relay protection tester.

Rapid technical support was essential to ensure that the commissioning schedule remained on track.

latest company case about Case Study: Six-Phase Relay Protection Tester Supports Commissioning at Zhuhai Combined Cycle Power Plant


Testing Equipment Used

The following equipment was used during the project:

  • HZJB Six-Phase Relay Protection Tester
  • Voltage and current output test leads
  • Generator synchronizing relay testing software
  • Auxiliary power fast transfer testing functions

The HZJB Six-Phase Relay Protection Tester supports automatic synchronization testing, protection relay verification, sequence testing, and programmable voltage/current output, making it suitable for substations, power plants, and industrial electrical systems.


Fast Transfer Device Testing

After arriving on site, HKVTEST engineers worked with the customer's commissioning team to test the auxiliary power fast transfer device.

The relay tester supplied simulated working power and standby power voltages.

During the test:

  • Rated voltage was applied to the normal power source.
  • The working source voltage was gradually reduced.
  • When the undervoltage threshold was reached, the fast transfer device automatically switched to the standby source.
  • Switching performance was smooth and stable without abnormal operation.

The test confirmed that the fast transfer system responded correctly according to the protection settings.

latest company case about Case Study: Six-Phase Relay Protection Tester Supports Commissioning at Zhuhai Combined Cycle Power Plant

Generator Synchronization Test

Following the plant shutdown and completion of safety procedures, synchronization testing was carried out for the generating units.

The combined cycle power plant consisted of:

Using the synchronization testing software built into the HZJB Six-Phase Relay Protection Tester, engineers simulated both electrical systems.

The tester allowed independent adjustment of:

Automatic synchronization mode was selected, enabling the synchronizing device to control voltage and frequency adjustments until synchronization conditions were achieved.

The synchronizing relay successfully issued the closing command once the following requirements were satisfied:

The synchronization process was completed successfully without abnormalities.


Relay Verification

Additional relay verification tests were performed using the relay tester's automatic ramp function.

Three relays installed in the synchronization control cabinet were tested.

Measured results showed:

Test Item Result
Pickup Voltage Approximately 74 V
Dropout Voltage Approximately 50 V
Relay Operation Passed

All measured values met the required commissioning specifications.


Technical Training

Besides completing the testing work, HKVTEST engineers also provided practical training for customer personnel.

The training covered:

The customer engineers were able to independently operate the tester after the training.


Project Results

The project was completed successfully with the following outcomes:


Why Professional Relay Testing Matters

Reliable relay protection testing helps ensure:

Professional relay testing equipment combined with experienced technical support can significantly reduce project delays and improve commissioning efficiency.


Related Product

HZJB Six-Phase Relay Protection Tester

Microprocessor Relay Protection Device for 10kV/35kV Substation


Conclusion

This project demonstrates how rapid equipment replacement, professional technical support, and advanced relay testing technology helped complete critical commissioning work at a combined cycle power plant.

The HZJB Six-Phase Relay Protection Tester provided stable performance throughout fast transfer testing, synchronization verification, and relay commissioning, enabling the customer to complete the project safely and efficiently.


Get in touch with us
Contact Person : fiona
Tel : +8618071531810
Fax : 86--17683804244
Characters Remaining(20/3000)